Referring to the SPC chart signals that a process is out of control, what type of problem does each signal indicate? List the signals.
 
  What will be an ideal response?

Question 2

Which of the following is true about forecast bias?
 
  A) It is the mean absolute deviation.
  B) It is equal to the square root of the MSE.
  C) When it is negative it means that the forecasts tended to be high.
  D) When it is positive it means that the forecasts tended to be high.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

SeanoH09

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

The signals that something has changed are:
1. one or more points outside the control limits
2. nine or more points in a row above or below the center line
3. six or more points moving in the same direction (up or down)
4. 14 points in a row, alternating up and down.

The first signal means that something has caused the process to produce a higher (or lower) measure than would be normally expected. This could be a problem with variability or a jump one way or the other in the process center. Only one such point above or below the control limits is needed to reach the conclusion that a special cause situation exists.

The second signal implies that the process center is drifting up or down. For example, this type of situation could occur in a process that is sensitive to temperature. If for some reason temperature gradually is increasing, the output measure will gradually change with the temperature change.

The third signal indicates that the process average has shifted (higher or lower) due to some special circumstance. For instance, a control setting may have been changed causing the output measures to increase or decrease consistently.

The fourth signal indicates something is causing the process to change between measurements.

Answer to Question 2

C




Beheh

  • Member
  • Posts: 520
Reply 2 on: Jun 24, 2018
YES! Correct, THANKS for helping me on my review


sarah_brady415

  • Member
  • Posts: 328
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

When Gabriel Fahrenheit invented the first mercury thermometer, he called "zero degrees" the lowest temperature he was able to attain with a mixture of ice and salt. For the upper point of his scale, he used 96°, which he measured as normal human body temperature (we know it to be 98.6° today because of more accurate thermometers).

Did you know?

The liver is the only organ that has the ability to regenerate itself after certain types of damage. As much as 25% of the liver can be removed, and it will still regenerate back to its original shape and size. However, the liver cannot regenerate after severe damage caused by alcohol.

Did you know?

Green tea is able to stop the scent of garlic or onion from causing bad breath.

Did you know?

Children with strabismus (crossed eyes) can be treated. They are not able to outgrow this condition on their own, but with help, it can be more easily corrected at a younger age. It is important for infants to have eye examinations as early as possible in their development and then another at age 2 years.

Did you know?

The first documented use of surgical anesthesia in the United States was in Connecticut in 1844.

For a complete list of videos, visit our video library