Author Question: ________ is an analytical method that determines the probabilities of the project completion times ... (Read 100 times)

lunatika

  • Hero Member
  • *****
  • Posts: 548
________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time
 
  is normal using the central limit theorem.A) Program Estimation and Research Technique
  B) Project Evaluation and Revise Technique
  C) Program Evaluation and Review Technique
  D) Project Estimation and Risk Technique

Question 2

Calculate the total number of television sets shipped from the plant in Arizona. (Hint: Use Solver)
 
  A) 1400 units
  B) 1350 units
  C) 1300 units
  D) 1250 units


zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Oliver Wendell Holmes is credited with introducing the words "anesthesia" and "anesthetic" into the English language in 1846.

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

Many medications that are used to treat infertility are injected subcutaneously. This is easy to do using the anterior abdomen as the site of injection but avoiding the area directly around the belly button.

Did you know?

Normal urine is sterile. It contains fluids, salts, and waste products. It is free of bacteria, viruses, and fungi.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

For a complete list of videos, visit our video library