You are the senior project manager for a Web development company with upwards of 100 current client projects. You have been assigned to evaluate two upcoming projects.
 
  One project is to develop a time- tracking solution that would allow your 20 freelancers to submit daily time sheets and would report on the time spent on each project. The other project is to redesign the client interface to the company extranet to make it easier to use. The extranet allows clients to log in and view their current Web sites under development, as well as view project statistics, documents, and progress reports. Compare the two projects in terms of risk factors.

Question 2

Measures defined by management and used to internally evaluate the success of a firm's financial, business process, customer, and learning and growth are called
 
  A) benchmarks.
  B) KPIs.
  C) the balanced scorecard method.
  D) BPM.
  E) parameters.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Viet Thy

  • Sr. Member
  • ****
  • Posts: 329
Answer to Question 1

Student answers will vary but should include an understanding of the main risks factors: size, structure, and technical expertise. An example answer is:
The main risk factors are size, structure, and technical expertise.
 Size. The time-tracking project is a larger project: It involves creating new programming that may interface with back-end systems and will immediately influence payment and cost. It also affects business processes. Redesigning an interface for the client extranet may simply be designing one or two pages that will be replicated for each client once the initial design is done.
 Structure. It may be easier to define the requirements of the time-tracking software, as this process is relatively straightforward. Understanding what makes the user interface problematic and defining ways to make it easier to use is somewhat of a less tangible quality than reporting on time, so this may be a concern in the second project.
 Technical expertise. Since the time-tracking project is a new application, there may be some issues of making sure any in-house staff has the appropriate level of expertise. The user interface involves working with existing programming that will not change. However, there may be a need to make sure that an expert who understands usability is present.

Answer to Question 2

B




michelleunicorn

  • Member
  • Posts: 565
Reply 2 on: Jul 7, 2018
:D TYSM


T4T

  • Member
  • Posts: 348
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

More than 150,000 Americans killed by cardiovascular disease are younger than the age of 65 years.

Did you know?

Critical care patients are twice as likely to receive the wrong medication. Of these errors, 20% are life-threatening, and 42% require additional life-sustaining treatments.

Did you know?

Acute bronchitis is an inflammation of the breathing tubes (bronchi), which causes increased mucus production and other changes. It is usually caused by bacteria or viruses, can be serious in people who have pulmonary or cardiac diseases, and can lead to pneumonia.

Did you know?

Patients who cannot swallow may receive nutrition via a parenteral route—usually, a catheter is inserted through the chest into a large vein going into the heart.

Did you know?

Russia has the highest death rate from cardiovascular disease followed by the Ukraine, Romania, Hungary, and Poland.

For a complete list of videos, visit our video library