Author Question: You are the senior project manager for a Web development company with upwards of 100 current client ... (Read 207 times)

michelleunicorn

  • Hero Member
  • *****
  • Posts: 565
You are the senior project manager for a Web development company with upwards of 100 current client projects. You have been assigned to evaluate two upcoming projects.
 
  One project is to develop a time- tracking solution that would allow your 20 freelancers to submit daily time sheets and would report on the time spent on each project. The other project is to redesign the client interface to the company extranet to make it easier to use. The extranet allows clients to log in and view their current Web sites under development, as well as view project statistics, documents, and progress reports. Compare the two projects in terms of risk factors.

Question 2

Measures defined by management and used to internally evaluate the success of a firm's financial, business process, customer, and learning and growth are called
 
  A) benchmarks.
  B) KPIs.
  C) the balanced scorecard method.
  D) BPM.
  E) parameters.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Viet Thy

  • Sr. Member
  • ****
  • Posts: 329
Answer to Question 1

Student answers will vary but should include an understanding of the main risks factors: size, structure, and technical expertise. An example answer is:
The main risk factors are size, structure, and technical expertise.
 Size. The time-tracking project is a larger project: It involves creating new programming that may interface with back-end systems and will immediately influence payment and cost. It also affects business processes. Redesigning an interface for the client extranet may simply be designing one or two pages that will be replicated for each client once the initial design is done.
 Structure. It may be easier to define the requirements of the time-tracking software, as this process is relatively straightforward. Understanding what makes the user interface problematic and defining ways to make it easier to use is somewhat of a less tangible quality than reporting on time, so this may be a concern in the second project.
 Technical expertise. Since the time-tracking project is a new application, there may be some issues of making sure any in-house staff has the appropriate level of expertise. The user interface involves working with existing programming that will not change. However, there may be a need to make sure that an expert who understands usability is present.

Answer to Question 2

B




michelleunicorn

  • Member
  • Posts: 565
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


mohan

  • Member
  • Posts: 362
Reply 3 on: Yesterday
Gracias!

 

Did you know?

In the United States, congenital cytomegalovirus causes one child to become disabled almost every hour. CMV is the leading preventable viral cause of development disability in newborns. These disabilities include hearing or vision loss, and cerebral palsy.

Did you know?

Bisphosphonates were first developed in the nineteenth century. They were first investigated for use in disorders of bone metabolism in the 1960s. They are now used clinically for the treatment of osteoporosis, Paget's disease, bone metastasis, multiple myeloma, and other conditions that feature bone fragility.

Did you know?

According to the FDA, adverse drug events harmed or killed approximately 1,200,000 people in the United States in the year 2015.

Did you know?

Atropine was named after the Greek goddess Atropos, the oldest and ugliest of the three sisters known as the Fates, who controlled the destiny of men.

Did you know?

Patients who cannot swallow may receive nutrition via a parenteral route—usually, a catheter is inserted through the chest into a large vein going into the heart.

For a complete list of videos, visit our video library