Author Question: Pessimistic time refers to: A) the maximum period of time for an activity to be completed. B) ... (Read 104 times)

Kikoku

  • Hero Member
  • *****
  • Posts: 540
Pessimistic time refers to:
 
  A) the maximum period of time for an activity to be completed.
  B) the minimum period of time for an activity to be completed.
  C) the planner's best guess of the amount of time the activity actually will require for completion.
  D) the maximum period of time for an entire project to be completed.
  E) the average period of time for an activity to be completed.

Question 2

Data cannot move directly from a source to a sink.
 
  Indicate whether the statement is true or false



dellikani2015

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

A
Explanation: A) When scheduling, if one considers that a task will take the maximum time this is pessimistic time.

Answer to Question 2

TRUE
Explanation: Data must be moved by a process.
CL



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The first oral chemotherapy drug for colon cancer was approved by FDA in 2001.

Did you know?

The U.S. Preventive Services Task Force recommends that all women age 65 years of age or older should be screened with bone densitometry.

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

The oldest recorded age was 122. Madame Jeanne Calment was born in France in 1875 and died in 1997. She was a vegetarian and loved olive oil, port wine, and chocolate.

Did you know?

Most childhood vaccines are 90–99% effective in preventing disease. Side effects are rarely serious.

For a complete list of videos, visit our video library