The term substantial completion, unless redefined in the Contract Documents, normally means that:
 
  A. the work is almost completed, but final completion will not occur until a later date.
   B. the contractor's obligations under the contract have been satisfied even though some minor items of pickup work remain.
   C. liquidated damage provisions of the contract still apply until all pickup (punch list) work is completed.
   D. the architect or engineer may not process final payment until a certificate of final completion is executed.
   E. none of the above.

Question 2

Contract documents usually include:
 
  A. shop drawings.
   B. trade standards.
   C. federal specifications.
   D. soils report.
   E. both B and C above.



1_Step_At_ATime

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

B

Answer to Question 2

E



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Studies show that systolic blood pressure can be significantly lowered by taking statins. In fact, the higher the patient's baseline blood pressure, the greater the effect of statins on his or her blood pressure.

Did you know?

Symptoms of kidney problems include a loss of appetite, back pain (which may be sudden and intense), chills, abdominal pain, fluid retention, nausea, the urge to urinate, vomiting, and fever.

Did you know?

Individuals are never “cured” of addictions. Instead, they learn how to manage their disease to lead healthy, balanced lives.

Did you know?

Anti-aging claims should not ever be believed. There is no supplement, medication, or any other substance that has been proven to slow or stop the aging process.

Did you know?

If all the neurons in the human body were lined up, they would stretch more than 600 miles.

For a complete list of videos, visit our video library