The term substantial completion, unless redefined in the Contract Documents, normally means that:
 
  A. the work is almost completed, but final completion will not occur until a later date.
   B. the contractor's obligations under the contract have been satisfied even though some minor items of pickup work remain.
   C. liquidated damage provisions of the contract still apply until all pickup (punch list) work is completed.
   D. the architect or engineer may not process final payment until a certificate of final completion is executed.
   E. none of the above.

Question 2

Contract documents usually include:
 
  A. shop drawings.
   B. trade standards.
   C. federal specifications.
   D. soils report.
   E. both B and C above.



1_Step_At_ATime

  • Sr. Member
  • ****
  • Posts: 342
Answer to Question 1

B

Answer to Question 2

E



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Street names for barbiturates include reds, red devils, yellow jackets, blue heavens, Christmas trees, and rainbows. They are commonly referred to as downers.

Did you know?

The human body produces and destroys 15 million blood cells every second.

Did you know?

Essential fatty acids have been shown to be effective against ulcers, asthma, dental cavities, and skin disorders such as acne.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

Did you know?

According to the Migraine Research Foundation, migraines are the third most prevalent illness in the world. Women are most affected (18%), followed by children of both sexes (10%), and men (6%).

For a complete list of videos, visit our video library