Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather than a definitive statement about how it will be done and when it will be completed?
 
  What will be an ideal response?

Question 2

___________________ strives to eliminate or minimize any process, operation or material usage that does not contribute to an efficient maintenance operation.
 
  A. corrective maintenance
  B. preventive maintenance
  C. lean maintenance
  D. JIT maintenance



vish98

  • Sr. Member
  • ****
  • Posts: 326
Answer to Question 1

The initial schedule is very similar to the estimate prepared by the
contractor. When the estimate is prepared, predictions will be made about how much
given items will cost. If the estimates are prepared judiciously, some items may
actually cost more but other items will cost less. The end result is that things average
out. The schedule is prepared with the same expectation, with some activities taking
longer that originally scheduled and others being completed in a shorter time.

An obvious variable that is impossible to predict with complete accuracy is the
weather. On sitework activities, an estimate might be made that the clearing will be
completed on a particular project in 12 working days. Perhaps an allowance was
included in the time estimate for rain. If no rain occurs, it might be possible to
complete the activity in 8 days. Of course, if very heavy rains plague the project for
two weeks, the project duration might extend to 20 days or more.

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

About one in five American adults and teenagers have had a genital herpes infection—and most of them don't know it. People with genital herpes have at least twice the risk of becoming infected with HIV if exposed to it than those people who do not have genital herpes.

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

Automated pill dispensing systems have alarms to alert patients when the correct dosing time has arrived. Most systems work with many varieties of medications, so patients who are taking a variety of drugs can still be in control of their dose regimen.

Did you know?

Certain chemicals, after ingestion, can be converted by the body into cyanide. Most of these chemicals have been removed from the market, but some old nail polish remover, solvents, and plastics manufacturing solutions can contain these substances.

Did you know?

Hyperthyroidism leads to an increased rate of metabolism and affects about 1% of women but only 0.1% of men. For most people, this increased metabolic rate causes the thyroid gland to become enlarged (known as a goiter).

For a complete list of videos, visit our video library