Author Question: Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather ... (Read 31 times)

karen

  • Hero Member
  • *****
  • Posts: 537
Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather than a definitive statement about how it will be done and when it will be completed?
 
  What will be an ideal response?

Question 2

___________________ strives to eliminate or minimize any process, operation or material usage that does not contribute to an efficient maintenance operation.
 
  A. corrective maintenance
  B. preventive maintenance
  C. lean maintenance
  D. JIT maintenance



vish98

  • Sr. Member
  • ****
  • Posts: 326
Answer to Question 1

The initial schedule is very similar to the estimate prepared by the
contractor. When the estimate is prepared, predictions will be made about how much
given items will cost. If the estimates are prepared judiciously, some items may
actually cost more but other items will cost less. The end result is that things average
out. The schedule is prepared with the same expectation, with some activities taking
longer that originally scheduled and others being completed in a shorter time.

An obvious variable that is impossible to predict with complete accuracy is the
weather. On sitework activities, an estimate might be made that the clearing will be
completed on a particular project in 12 working days. Perhaps an allowance was
included in the time estimate for rain. If no rain occurs, it might be possible to
complete the activity in 8 days. Of course, if very heavy rains plague the project for
two weeks, the project duration might extend to 20 days or more.

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Pubic lice (crabs) are usually spread through sexual contact. You cannot catch them by using a public toilet.

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

The human body produces and destroys 15 million blood cells every second.

Did you know?

Once thought to have neurofibromatosis, Joseph Merrick (also known as "the elephant man") is now, in retrospect, thought by clinical experts to have had Proteus syndrome. This endocrine disease causes continued and abnormal growth of the bones, muscles, skin, and so on and can become completely debilitating with severe deformities occurring anywhere on the body.

Did you know?

Illicit drug use costs the United States approximately $181 billion every year.

For a complete list of videos, visit our video library