Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather than a definitive statement about how it will be done and when it will be completed?
 
  What will be an ideal response?

Question 2

___________________ strives to eliminate or minimize any process, operation or material usage that does not contribute to an efficient maintenance operation.
 
  A. corrective maintenance
  B. preventive maintenance
  C. lean maintenance
  D. JIT maintenance



vish98

  • Sr. Member
  • ****
  • Posts: 326
Answer to Question 1

The initial schedule is very similar to the estimate prepared by the
contractor. When the estimate is prepared, predictions will be made about how much
given items will cost. If the estimates are prepared judiciously, some items may
actually cost more but other items will cost less. The end result is that things average
out. The schedule is prepared with the same expectation, with some activities taking
longer that originally scheduled and others being completed in a shorter time.

An obvious variable that is impossible to predict with complete accuracy is the
weather. On sitework activities, an estimate might be made that the clearing will be
completed on a particular project in 12 working days. Perhaps an allowance was
included in the time estimate for rain. If no rain occurs, it might be possible to
complete the activity in 8 days. Of course, if very heavy rains plague the project for
two weeks, the project duration might extend to 20 days or more.

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

HIV testing reach is still limited. An estimated 40% of people with HIV (more than 14 million) remain undiagnosed and do not know their infection status.

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

The Food and Drug Administration has approved Risperdal, an adult antipsychotic drug, for the symptomatic treatment of irritability in children and adolescents with autism. The approval is the first for the use of a drug to treat behaviors associated with autism in children. These behaviors are included under the general heading of irritability and include aggression, deliberate self-injury, and temper tantrums.

Did you know?

Bacteria have flourished on the earth for over three billion years. They were the first life forms on the planet.

For a complete list of videos, visit our video library