Author Question: Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather ... (Read 36 times)

karen

  • Hero Member
  • *****
  • Posts: 537
Why is the initial schedule to be viewed as a best guess of how a project will be constructed rather than a definitive statement about how it will be done and when it will be completed?
 
  What will be an ideal response?

Question 2

___________________ strives to eliminate or minimize any process, operation or material usage that does not contribute to an efficient maintenance operation.
 
  A. corrective maintenance
  B. preventive maintenance
  C. lean maintenance
  D. JIT maintenance



vish98

  • Sr. Member
  • ****
  • Posts: 326
Answer to Question 1

The initial schedule is very similar to the estimate prepared by the
contractor. When the estimate is prepared, predictions will be made about how much
given items will cost. If the estimates are prepared judiciously, some items may
actually cost more but other items will cost less. The end result is that things average
out. The schedule is prepared with the same expectation, with some activities taking
longer that originally scheduled and others being completed in a shorter time.

An obvious variable that is impossible to predict with complete accuracy is the
weather. On sitework activities, an estimate might be made that the clearing will be
completed on a particular project in 12 working days. Perhaps an allowance was
included in the time estimate for rain. If no rain occurs, it might be possible to
complete the activity in 8 days. Of course, if very heavy rains plague the project for
two weeks, the project duration might extend to 20 days or more.

Answer to Question 2

C



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Only one in 10 cancer deaths is caused by the primary tumor. The vast majority of cancer mortality is caused by cells breaking away from the main tumor and metastasizing to other parts of the body, such as the brain, bones, or liver.

Did you know?

Signs of depression include feeling sad most of the time for 2 weeks or longer; loss of interest in things normally enjoyed; lack of energy; sleep and appetite disturbances; weight changes; feelings of hopelessness, helplessness, or worthlessness; an inability to make decisions; and thoughts of death and suicide.

Did you know?

The tallest man ever known was Robert Wadlow, an American, who reached the height of 8 feet 11 inches. He died at age 26 years from an infection caused by the immense weight of his body (491 pounds) and the stress on his leg bones and muscles.

Did you know?

Automated pill dispensing systems have alarms to alert patients when the correct dosing time has arrived. Most systems work with many varieties of medications, so patients who are taking a variety of drugs can still be in control of their dose regimen.

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

For a complete list of videos, visit our video library