This topic contains a solution. Click here to go to the answer

Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 367 times)

mmm

  • Hero Member
  • *****
  • Posts: 558

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the project finishing time is
◦ 20 hours.
◦ 18 hours.
◦ 17 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 5 hours.
◦ 3 hours.
◦ 7 hours.
◦ 1 hour.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

samiel-sayed

  • Sr. Member
  • ****
  • Posts: 337

itsmyluck

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors, the project finishing time is
◦ 12 hours.
◦ 13 hours.
◦ 11 hours.
◦ 14 hours.
◦ none of these

Question 2

A project consists of five tasks. The lengths of the tasks (in hours) are 5, 4, 4, 3, and 3. The tasks are all independent (i.e., there are no precedence relations).

Using the critical-path algorithm to schedule the project with two processors, the finishing time is
◦ 12 hours.
◦ 9 hours.
◦ 10 hours.
◦ 11 hours.
◦ none of these



olderstudent

  • Sr. Member
  • ****
  • Posts: 339

 

Did you know?

A strange skin disease referred to as Morgellons has occurred in the southern United States and in California. Symptoms include slowly healing sores, joint pain, persistent fatigue, and a sensation of things crawling through the skin. Another symptom is strange-looking, threadlike extrusions coming out of the skin.

Did you know?

Common abbreviations that cause medication errors include U (unit), mg (milligram), QD (every day), SC (subcutaneous), TIW (three times per week), D/C (discharge or discontinue), HS (at bedtime or "hours of sleep"), cc (cubic centimeters), and AU (each ear).

Did you know?

There are approximately 3 million unintended pregnancies in the United States each year.

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

Essential fatty acids have been shown to be effective against ulcers, asthma, dental cavities, and skin disorders such as acne.

For a complete list of videos, visit our video library