Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 26 hours.
◦ 22 hours.
◦ none of these