Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 1195 times)

audragclark

  • Hero Member
  • *****
  • Posts: 579

Question 1

Suppose you have the project consisting of the six tasks described in the following table.




Which project digraph below models the project described?












◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 8.
◦ 6.
◦ 9.
◦ 7.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by audragclark on May 5, 2020

xthemafja

  • Sr. Member
  • ****
  • Posts: 348
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 50% of students answer this correctly



maychende

  • Hero Member
  • *****
  • Posts: 556

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 7.
◦ 9.
◦ 8.
◦ 10.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




What is the number of tasks in this project?
◦ 11
◦ 9
◦ 6
◦ 7
◦ none of these




ts19998

  • Hero Member
  • *****
  • Posts: 531
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, F, E, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




burchfield96

  • Hero Member
  • *****
  • Posts: 610
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 26 hours.
◦ 22 hours.
◦ none of these




misspop

  • Hero Member
  • *****
  • Posts: 540
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project finishing time is
◦ 22 hours.
◦ 17 hours.
◦ 18 hours.
◦ 21 hours.
◦ none of these




 

Did you know?

Less than one of every three adults with high LDL cholesterol has the condition under control. Only 48.1% with the condition are being treated for it.

Did you know?

For pediatric patients, intravenous fluids are the most commonly cited products involved in medication errors that are reported to the USP.

Did you know?

Everyone has one nostril that is larger than the other.

Did you know?

Signs and symptoms of a drug overdose include losing consciousness, fever or sweating, breathing problems, abnormal pulse, and changes in skin color.

Did you know?

Thyroid conditions may make getting pregnant impossible.

For a complete list of videos, visit our video library