Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Scheduling this project with two processors results in a finishing time shorter than 22 hours using the priority list
◦ C, B, A, F, E, D.
◦ C, F, A, B, D, E.
◦ C, D, B, E, A, F.
◦ C, F, E, B, A, D.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

naturalchemist

  • Hero Member
  • *****
  • Posts: 542
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



momo1250

  • Sr. Member
  • ****
  • Posts: 338
task A to one processor, task B to the other one.



kodithompson

  • Hero Member
  • *****
  • Posts: 566

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project timeline is








◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a completion time of
◦ 18 hours.
◦ 22 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




fox

  • Hero Member
  • *****
  • Posts: 540

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 26 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
◦ task B to one processor, task C to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ none of these



wtf444

  • Sr. Member
  • ****
  • Posts: 314

Answer 1

26 hours.

Answer 2

task A to one processor, task C to the other one.



Melani1276

  • Hero Member
  • *****
  • Posts: 516

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the project finishing time is
◦ 18 hours.
◦ 17 hours.
◦ 20 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 1 hour.
◦ 7 hours.
◦ 5 hours.
◦ 3 hours.
◦ none of these



Jane

  • Sr. Member
  • ****
  • Posts: 309

 

Did you know?

Patients should never assume they are being given the appropriate drugs. They should make sure they know which drugs are being prescribed, and always double-check that the drugs received match the prescription.

Did you know?

People who have myopia, or nearsightedness, are not able to see objects at a distance but only up close. It occurs when the cornea is either curved too steeply, the eye is too long, or both. This condition is progressive and worsens with time. More than 100 million people in the United States are nearsighted, but only 20% of those are born with the condition. Diet, eye exercise, drug therapy, and corrective lenses can all help manage nearsightedness.

Did you know?

Less than one of every three adults with high LDL cholesterol has the condition under control. Only 48.1% with the condition are being treated for it.

Did you know?

Limit intake of red meat and dairy products made with whole milk. Choose skim milk, low-fat or fat-free dairy products. Limit fried food. Use healthy oils when cooking.

Did you know?

More than one-third of adult Americans are obese. Diseases that kill the largest number of people annually, such as heart disease, cancer, diabetes, stroke, and hypertension, can be attributed to diet.

For a complete list of videos, visit our video library