Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Scheduling this project with two processors results in a finishing time shorter than 22 hours using the priority list
◦ C, B, A, F, E, D.
◦ C, F, A, B, D, E.
◦ C, D, B, E, A, F.
◦ C, F, E, B, A, D.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

naturalchemist

  • Hero Member
  • *****
  • Posts: 542
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



momo1250

  • Sr. Member
  • ****
  • Posts: 338
task A to one processor, task B to the other one.



kodithompson

  • Hero Member
  • *****
  • Posts: 566

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project timeline is








◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a completion time of
◦ 18 hours.
◦ 22 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




fox

  • Hero Member
  • *****
  • Posts: 540

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 26 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
◦ task B to one processor, task C to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ none of these



wtf444

  • Sr. Member
  • ****
  • Posts: 314

Answer 1

26 hours.

Answer 2

task A to one processor, task C to the other one.



Melani1276

  • Hero Member
  • *****
  • Posts: 516

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the project finishing time is
◦ 18 hours.
◦ 17 hours.
◦ 20 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 1 hour.
◦ 7 hours.
◦ 5 hours.
◦ 3 hours.
◦ none of these



Jane

  • Sr. Member
  • ****
  • Posts: 309

 

Did you know?

Patients should never assume they are being given the appropriate drugs. They should make sure they know which drugs are being prescribed, and always double-check that the drugs received match the prescription.

Did you know?

Giardia is one of the most common intestinal parasites worldwide, and infects up to 20% of the world population, mostly in poorer countries with inadequate sanitation. Infections are most common in children, though chronic Giardia is more common in adults.

Did you know?

Automated pill dispensing systems have alarms to alert patients when the correct dosing time has arrived. Most systems work with many varieties of medications, so patients who are taking a variety of drugs can still be in control of their dose regimen.

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

Medications that are definitely not safe to take when breastfeeding include radioactive drugs, antimetabolites, some cancer (chemotherapy) agents, bromocriptine, ergotamine, methotrexate, and cyclosporine.

For a complete list of videos, visit our video library