Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 985 times)

Deast7027

  • Hero Member
  • *****
  • Posts: 538
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Scheduling this project with two processors results in a finishing time shorter than 22 hours using the priority list
◦ C, B, A, F, E, D.
◦ C, F, A, B, D, E.
◦ C, D, B, E, A, F.
◦ C, F, E, B, A, D.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

naturalchemist

  • Hero Member
  • *****
  • Posts: 542
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



momo1250

  • Sr. Member
  • ****
  • Posts: 338
task A to one processor, task B to the other one.



kodithompson

  • Hero Member
  • *****
  • Posts: 566

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project timeline is








◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a completion time of
◦ 18 hours.
◦ 22 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




fox

  • Hero Member
  • *****
  • Posts: 540

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 26 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
◦ task B to one processor, task C to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ none of these



wtf444

  • Sr. Member
  • ****
  • Posts: 314

Answer 1

26 hours.

Answer 2

task A to one processor, task C to the other one.



Melani1276

  • Hero Member
  • *****
  • Posts: 516

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the project finishing time is
◦ 18 hours.
◦ 17 hours.
◦ 20 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 1 hour.
◦ 7 hours.
◦ 5 hours.
◦ 3 hours.
◦ none of these



Jane

  • Sr. Member
  • ****
  • Posts: 309

 

Did you know?

Amoebae are the simplest type of protozoans, and are characterized by a feeding and dividing trophozoite stage that moves by temporary extensions called pseudopodia or false feet.

Did you know?

Recent studies have shown that the number of medication errors increases in relation to the number of orders that are verified per pharmacist, per work shift.

Did you know?

The cure for trichomoniasis is easy as long as the patient does not drink alcoholic beverages for 24 hours. Just a single dose of medication is needed to rid the body of the disease. However, without proper precautions, an individual may contract the disease repeatedly. In fact, most people develop trichomoniasis again within three months of their last treatment.

Did you know?

Always store hazardous household chemicals in their original containers out of reach of children. These include bleach, paint, strippers and products containing turpentine, garden chemicals, oven cleaners, fondue fuels, nail polish, and nail polish remover.

Did you know?

Never take aspirin without food because it is likely to irritate your stomach. Never give aspirin to children under age 12. Overdoses of aspirin have the potential to cause deafness.

For a complete list of videos, visit our video library