Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Scheduling this project with two processors results in a finishing time shorter than 22 hours using the priority list
◦ C, B, A, F, E, D.
◦ C, F, A, B, D, E.
◦ C, D, B, E, A, F.
◦ C, F, E, B, A, D.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

naturalchemist

  • Hero Member
  • *****
  • Posts: 542
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



momo1250

  • Sr. Member
  • ****
  • Posts: 338
task A to one processor, task B to the other one.



kodithompson

  • Hero Member
  • *****
  • Posts: 566

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project timeline is








◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a completion time of
◦ 18 hours.
◦ 22 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




fox

  • Hero Member
  • *****
  • Posts: 540

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 26 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
◦ task B to one processor, task C to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ none of these



wtf444

  • Sr. Member
  • ****
  • Posts: 314

Answer 1

26 hours.

Answer 2

task A to one processor, task C to the other one.



Melani1276

  • Hero Member
  • *****
  • Posts: 516

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the project finishing time is
◦ 18 hours.
◦ 17 hours.
◦ 20 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 1 hour.
◦ 7 hours.
◦ 5 hours.
◦ 3 hours.
◦ none of these



Jane

  • Sr. Member
  • ****
  • Posts: 309

 

Did you know?

About 100 new prescription or over-the-counter drugs come into the U.S. market every year.

Did you know?

Automated pill dispensing systems have alarms to alert patients when the correct dosing time has arrived. Most systems work with many varieties of medications, so patients who are taking a variety of drugs can still be in control of their dose regimen.

Did you know?

Not getting enough sleep can greatly weaken the immune system. Lack of sleep makes you more likely to catch a cold, or more difficult to fight off an infection.

Did you know?

Your heart beats over 36 million times a year.

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

For a complete list of videos, visit our video library