Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Scheduling this project with two processors results in a finishing time shorter than 22 hours using the priority list
◦ C, B, A, F, E, D.
◦ C, F, A, B, D, E.
◦ C, D, B, E, A, F.
◦ C, F, E, B, A, D.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

naturalchemist

  • Hero Member
  • *****
  • Posts: 542
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



momo1250

  • Sr. Member
  • ****
  • Posts: 338
task A to one processor, task B to the other one.



kodithompson

  • Hero Member
  • *****
  • Posts: 566

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project timeline is








◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a completion time of
◦ 18 hours.
◦ 22 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




fox

  • Hero Member
  • *****
  • Posts: 540

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 26 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
◦ task B to one processor, task C to the other one.
◦ task B to one processor, task E to the other one.
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ none of these



wtf444

  • Sr. Member
  • ****
  • Posts: 314

Answer 1

26 hours.

Answer 2

task A to one processor, task C to the other one.



Melani1276

  • Hero Member
  • *****
  • Posts: 516

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the project finishing time is
◦ 18 hours.
◦ 17 hours.
◦ 20 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the decreasing-time algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 1 hour.
◦ 7 hours.
◦ 5 hours.
◦ 3 hours.
◦ none of these



Jane

  • Sr. Member
  • ****
  • Posts: 309

 

Did you know?

Elderly adults are at greatest risk of stroke and myocardial infarction and have the most to gain from prophylaxis. Patients ages 60 to 80 years with blood pressures above 160/90 mm Hg should benefit from antihypertensive treatment.

Did you know?

Chronic marijuana use can damage the white blood cells and reduce the immune system's ability to respond to disease by as much as 40%. Without a strong immune system, the body is vulnerable to all kinds of degenerative and infectious diseases.

Did you know?

Drying your hands with a paper towel will reduce the bacterial count on your hands by 45–60%.

Did you know?

Amphetamine poisoning can cause intravascular coagulation, circulatory collapse, rhabdomyolysis, ischemic colitis, acute psychosis, hyperthermia, respiratory distress syndrome, and pericarditis.

Did you know?

The longest a person has survived after a heart transplant is 24 years.

For a complete list of videos, visit our video library