Suppose you have the project consisting of the six tasks described in the following table.




Which project digraph below models the project described?












◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 8.
◦ 6.
◦ 9.
◦ 7.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by audragclark on May 5, 2020

xthemafja

  • Sr. Member
  • ****
  • Posts: 348
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 50% of students answer this correctly



maychende

  • Hero Member
  • *****
  • Posts: 556

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The number of tasks in the project is
◦ 7.
◦ 9.
◦ 8.
◦ 10.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




What is the number of tasks in this project?
◦ 11
◦ 9
◦ 6
◦ 7
◦ none of these




ts19998

  • Hero Member
  • *****
  • Posts: 531
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, F, E, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 22 hours.
◦ 18 hours.
◦ 23 hours.
◦ 19 hours.
◦ none of these




burchfield96

  • Hero Member
  • *****
  • Posts: 610
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list, C, E, G, F, B, A, D and the priority-list model to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 26 hours.
◦ 22 hours.
◦ none of these




misspop

  • Hero Member
  • *****
  • Posts: 540
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the priority list F, E, A, D, B, G, C and the priority-list model to schedule this project with two processors, the project finishing time is
◦ 22 hours.
◦ 17 hours.
◦ 18 hours.
◦ 21 hours.
◦ none of these




 

Did you know?

Adults are resistant to the bacterium that causes Botulism. These bacteria thrive in honey – therefore, honey should never be given to infants since their immune systems are not yet resistant.

Did you know?

The average older adult in the United States takes five prescription drugs per day. Half of these drugs contain a sedative. Alcohol should therefore be avoided by most senior citizens because of the dangerous interactions between alcohol and sedatives.

Did you know?

Chronic marijuana use can damage the white blood cells and reduce the immune system's ability to respond to disease by as much as 40%. Without a strong immune system, the body is vulnerable to all kinds of degenerative and infectious diseases.

Did you know?

Asthma cases in Americans are about 75% higher today than they were in 1980.

Did you know?

Amoebae are the simplest type of protozoans, and are characterized by a feeding and dividing trophozoite stage that moves by temporary extensions called pseudopodia or false feet.

For a complete list of videos, visit our video library