Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 23 hours.
◦ 19 hours.
◦ 18 hours.
◦ 22 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with six processors results in a finishing time of
◦ 23 hours.
◦ 18 hours.
◦ 22 hours.
◦ 19 hours.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

triiciiaa

  • Sr. Member
  • ****
  • Posts: 349

beccaep

  • Hero Member
  • *****
  • Posts: 535

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from E is
◦ 9 hours.
◦ 2 hours.
◦ 6 hours.
◦ 8 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 13 hours.
◦ 18 hours.
◦ 5 hours.
◦ 21 hours.
◦ none of these



perkiness

  • Sr. Member
  • ****
  • Posts: 348

nramada

  • Hero Member
  • *****
  • Posts: 580

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 17 hours.
◦ 26 hours.
◦ 21 hours.
◦ 18 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 22 hours.
◦ 26 hours.
◦ none of these



princessflame2016

  • Sr. Member
  • ****
  • Posts: 298

yoooooman

  • Hero Member
  • *****
  • Posts: 557

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 22 hours.
◦ 21 hours.
◦ 24 hours.
◦ 20 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with five processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 20 hours.
◦ none of these



apple

  • Sr. Member
  • ****
  • Posts: 352

CQXA

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path of this project digraph is
◦ 11 hours.
◦ 16 hours.
◦ 12 hours.
◦ 14 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the critical-path algorithm to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



jaaaaaaa

  • Sr. Member
  • ****
  • Posts: 341

Answer 1

14 hours.

Answer 2

task B to one processor, task C to the other one.



 

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Before a vaccine is licensed in the USA, the Food and Drug Administration (FDA) reviews it for safety and effectiveness. The CDC then reviews all studies again, as well as the American Academy of Pediatrics and the American Academy of Family Physicians. Every lot of vaccine is tested before administration to the public, and the FDA regularly inspects vaccine manufacturers' facilities.

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

Did you know?

The newest statin drug, rosuvastatin, has been called a superstatin because it appears to reduce LDL cholesterol to a greater degree than the other approved statin drugs.

Did you know?

Fungal nail infections account for up to 30% of all skin infections. They affect 5% of the general population—mostly people over the age of 70.

For a complete list of videos, visit our video library