Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 363 times)

cherise1989

  • Hero Member
  • *****
  • Posts: 555

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 23 hours.
◦ 19 hours.
◦ 18 hours.
◦ 22 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with six processors results in a finishing time of
◦ 23 hours.
◦ 18 hours.
◦ 22 hours.
◦ 19 hours.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

triiciiaa

  • Sr. Member
  • ****
  • Posts: 349

beccaep

  • Hero Member
  • *****
  • Posts: 535

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from E is
◦ 9 hours.
◦ 2 hours.
◦ 6 hours.
◦ 8 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 13 hours.
◦ 18 hours.
◦ 5 hours.
◦ 21 hours.
◦ none of these



perkiness

  • Sr. Member
  • ****
  • Posts: 348

nramada

  • Hero Member
  • *****
  • Posts: 580

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 17 hours.
◦ 26 hours.
◦ 21 hours.
◦ 18 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 22 hours.
◦ 26 hours.
◦ none of these



princessflame2016

  • Sr. Member
  • ****
  • Posts: 298

yoooooman

  • Hero Member
  • *****
  • Posts: 557

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 22 hours.
◦ 21 hours.
◦ 24 hours.
◦ 20 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with five processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 20 hours.
◦ none of these



apple

  • Sr. Member
  • ****
  • Posts: 352

CQXA

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path of this project digraph is
◦ 11 hours.
◦ 16 hours.
◦ 12 hours.
◦ 14 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the critical-path algorithm to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



jaaaaaaa

  • Sr. Member
  • ****
  • Posts: 341

Answer 1

14 hours.

Answer 2

task B to one processor, task C to the other one.



 

Did you know?

Multiple sclerosis is a condition wherein the body's nervous system is weakened by an autoimmune reaction that attacks the myelin sheaths of neurons.

Did you know?

The first successful kidney transplant was performed in 1954 and occurred in Boston. A kidney from an identical twin was transplanted into his dying brother's body and was not rejected because it did not appear foreign to his body.

Did you know?

During the twentieth century, a variant of the metric system was used in Russia and France in which the base unit of mass was the tonne. Instead of kilograms, this system used millitonnes (mt).

Did you know?

Walt Disney helped combat malaria by making an animated film in 1943 called The Winged Scourge. This short film starred the seven dwarfs and taught children that mosquitos transmit malaria, which is a very bad disease. It advocated the killing of mosquitos to stop the disease.

Did you know?

Hyperthyroidism leads to an increased rate of metabolism and affects about 1% of women but only 0.1% of men. For most people, this increased metabolic rate causes the thyroid gland to become enlarged (known as a goiter).

For a complete list of videos, visit our video library