Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 23 hours.
◦ 19 hours.
◦ 18 hours.
◦ 22 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with six processors results in a finishing time of
◦ 23 hours.
◦ 18 hours.
◦ 22 hours.
◦ 19 hours.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

triiciiaa

  • Sr. Member
  • ****
  • Posts: 349

beccaep

  • Hero Member
  • *****
  • Posts: 535

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from E is
◦ 9 hours.
◦ 2 hours.
◦ 6 hours.
◦ 8 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 13 hours.
◦ 18 hours.
◦ 5 hours.
◦ 21 hours.
◦ none of these



perkiness

  • Sr. Member
  • ****
  • Posts: 348

nramada

  • Hero Member
  • *****
  • Posts: 580

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 17 hours.
◦ 26 hours.
◦ 21 hours.
◦ 18 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 22 hours.
◦ 26 hours.
◦ none of these



princessflame2016

  • Sr. Member
  • ****
  • Posts: 298

yoooooman

  • Hero Member
  • *****
  • Posts: 557

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 22 hours.
◦ 21 hours.
◦ 24 hours.
◦ 20 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with five processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 20 hours.
◦ none of these



apple

  • Sr. Member
  • ****
  • Posts: 352

CQXA

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path of this project digraph is
◦ 11 hours.
◦ 16 hours.
◦ 12 hours.
◦ 14 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the critical-path algorithm to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



jaaaaaaa

  • Sr. Member
  • ****
  • Posts: 341

Answer 1

14 hours.

Answer 2

task B to one processor, task C to the other one.



 

Did you know?

Approximately 500,000 babies are born each year in the United States to teenage mothers.

Did you know?

People with high total cholesterol have about two times the risk for heart disease as people with ideal levels.

Did you know?

Patients should never assume they are being given the appropriate drugs. They should make sure they know which drugs are being prescribed, and always double-check that the drugs received match the prescription.

Did you know?

For about 100 years, scientists thought that peptic ulcers were caused by stress, spicy food, and alcohol. Later, researchers added stomach acid to the list of causes and began treating ulcers with antacids. Now it is known that peptic ulcers are predominantly caused by Helicobacter pylori, a spiral-shaped bacterium that normally exist in the stomach.

Did you know?

Earwax has antimicrobial properties that reduce the viability of bacteria and fungus in the human ear.

For a complete list of videos, visit our video library