Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 1222 times)

cherise1989

  • Hero Member
  • *****
  • Posts: 555

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 23 hours.
◦ 19 hours.
◦ 18 hours.
◦ 22 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with six processors results in a finishing time of
◦ 23 hours.
◦ 18 hours.
◦ 22 hours.
◦ 19 hours.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

triiciiaa

  • Sr. Member
  • ****
  • Posts: 349

beccaep

  • Hero Member
  • *****
  • Posts: 535

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from E is
◦ 9 hours.
◦ 2 hours.
◦ 6 hours.
◦ 8 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path from B is
◦ 13 hours.
◦ 18 hours.
◦ 5 hours.
◦ 21 hours.
◦ none of these



perkiness

  • Sr. Member
  • ****
  • Posts: 348

nramada

  • Hero Member
  • *****
  • Posts: 580

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path for the entire project is
◦ 17 hours.
◦ 26 hours.
◦ 21 hours.
◦ 18 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using critical-path algorithm to schedule this project with two processors results in a finishing time of
◦ 24 hours.
◦ 21 hours.
◦ 22 hours.
◦ 26 hours.
◦ none of these



princessflame2016

  • Sr. Member
  • ****
  • Posts: 298

yoooooman

  • Hero Member
  • *****
  • Posts: 557

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors results in a finishing time of
◦ 22 hours.
◦ 21 hours.
◦ 24 hours.
◦ 20 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with five processors results in a finishing time of
◦ 24 hours.
◦ 22 hours.
◦ 21 hours.
◦ 20 hours.
◦ none of these



apple

  • Sr. Member
  • ****
  • Posts: 352

CQXA

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




The length of the critical path of this project digraph is
◦ 11 hours.
◦ 16 hours.
◦ 12 hours.
◦ 14 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




If we use the critical-path algorithm to schedule this project with two processors, we should start by assigning
◦ task A to one processor, task C to the other one.
◦ task A to one processor, task B to the other one.
◦ task B to one processor, task E to the other one.
◦ task B to one processor, task C to the other one.
◦ none of these



jaaaaaaa

  • Sr. Member
  • ****
  • Posts: 341

Answer 1

14 hours.

Answer 2

task B to one processor, task C to the other one.



 

Did you know?

Stroke kills people from all ethnic backgrounds, but the people at highest risk for fatal strokes are: black men, black women, Asian men, white men, and white women.

Did you know?

More than 20 million Americans cite use of marijuana within the past 30 days, according to the National Survey on Drug Use and Health (NSDUH). More than 8 million admit to using it almost every day.

Did you know?

Though the United States has largely rejected the metric system, it is used for currency, as in 100 pennies = 1 dollar. Previously, the British currency system was used, with measurements such as 12 pence to the shilling, and 20 shillings to the pound.

Did you know?

Addicts to opiates often avoid treatment because they are afraid of withdrawal. Though unpleasant, with proper management, withdrawal is rarely fatal and passes relatively quickly.

Did you know?

Vaccines prevent between 2.5 and 4 million deaths every year.

For a complete list of videos, visit our video library