Author Question: ________ is an analytical method that determines the probabilities of the project completion times ... (Read 86 times)

lunatika

  • Hero Member
  • *****
  • Posts: 548
________ is an analytical method that determines the probabilities of the project completion times in project management models by assuming that the expected activity times define the critical path and that the distribution of project completion time
 
  is normal using the central limit theorem.A) Program Estimation and Research Technique
  B) Project Evaluation and Revise Technique
  C) Program Evaluation and Review Technique
  D) Project Estimation and Risk Technique

Question 2

Calculate the total number of television sets shipped from the plant in Arizona. (Hint: Use Solver)
 
  A) 1400 units
  B) 1350 units
  C) 1300 units
  D) 1250 units


zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

C

Answer to Question 2

D



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Limit intake of red meat and dairy products made with whole milk. Choose skim milk, low-fat or fat-free dairy products. Limit fried food. Use healthy oils when cooking.

Did you know?

The shortest mature adult human of whom there is independent evidence was Gul Mohammed in India. In 1990, he was measured in New Delhi and stood 22.5 inches tall.

Did you know?

The types of cancer that alpha interferons are used to treat include hairy cell leukemia, melanoma, follicular non-Hodgkin's lymphoma, and AIDS-related Kaposi's sarcoma.

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

Did you know?

Of the estimated 2 million heroin users in the United States, 600,000–800,000 are considered hardcore addicts. Heroin addiction is considered to be one of the hardest addictions to recover from.

For a complete list of videos, visit our video library