Author Question: Resource requirements planning (RRP) a. is a long-run, macro-level planning tool. b. checks the ... (Read 82 times)

HudsonKB16

  • Hero Member
  • *****
  • Posts: 535
Resource requirements planning (RRP)
 a. is a long-run, macro-level planning tool.
  b. checks the feasibility of the master production schedule.
  c. checks the feasibility of the materials requirement plan.
  d. is a long-range materials plan that translates annual business plans.

Question 2

Which of the following is NOT one of the biggest B2C catalogers?
 a. Sears
  b. JCPenney
  c. Williams-Sonoma
  d. The Limited



soda0602

  • Sr. Member
  • ****
  • Posts: 313
Answer to Question 1

a

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Cyanide works by making the human body unable to use oxygen.

Did you know?

Warfarin was developed as a consequence of the study of a strange bleeding disorder that suddenly occurred in cattle on the northern prairies of the United States in the early 1900s.

Did you know?

Before a vaccine is licensed in the USA, the Food and Drug Administration (FDA) reviews it for safety and effectiveness. The CDC then reviews all studies again, as well as the American Academy of Pediatrics and the American Academy of Family Physicians. Every lot of vaccine is tested before administration to the public, and the FDA regularly inspects vaccine manufacturers' facilities.

Did you know?

Malaria was not eliminated in the United States until 1951. The term eliminated means that no new cases arise in a country for 3 years.

Did you know?

The first war in which wide-scale use of anesthetics occurred was the Civil War, and 80% of all wounds were in the extremities.

For a complete list of videos, visit our video library