Author Question: Resource requirements planning (RRP) a. is a long-run, macro-level planning tool. b. checks the ... (Read 88 times)

HudsonKB16

  • Hero Member
  • *****
  • Posts: 535
Resource requirements planning (RRP)
 a. is a long-run, macro-level planning tool.
  b. checks the feasibility of the master production schedule.
  c. checks the feasibility of the materials requirement plan.
  d. is a long-range materials plan that translates annual business plans.

Question 2

Which of the following is NOT one of the biggest B2C catalogers?
 a. Sears
  b. JCPenney
  c. Williams-Sonoma
  d. The Limited



soda0602

  • Sr. Member
  • ****
  • Posts: 313
Answer to Question 1

a

Answer to Question 2

d



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Every 10 seconds, a person in the United States goes to the emergency room complaining of head pain. About 1.2 million visits are for acute migraine attacks.

Did you know?

Many of the drugs used by neuroscientists are derived from toxic plants and venomous animals (such as snakes, spiders, snails, and puffer fish).

Did you know?

Eat fiber! A diet high in fiber can help lower cholesterol levels by as much as 10%.

Did you know?

As many as 20% of Americans have been infected by the fungus known as Histoplasmosis. While most people are asymptomatic or only have slight symptoms, infection can progress to a rapid and potentially fatal superinfection.

Did you know?

Illness; diuretics; laxative abuse; hot weather; exercise; sweating; caffeine; alcoholic beverages; starvation diets; inadequate carbohydrate consumption; and diets high in protein, salt, or fiber can cause people to become dehydrated.

For a complete list of videos, visit our video library