Establishing cost control is part of the _____ phase.
 
  A) bidding
  B) pre-construction
  C) construction
  D) closeout

Question 2

Which delivery system involves the owner, architect/engineer, and general contractor?
 
  A) The traditional contract delivery system
  B) The design-build system
  C) The construction management system (CM)
  D) The engineering-procurement-construction (E-P-C) system



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

harveenkau8139

  • Sr. Member
  • ****
  • Posts: 304
Answer to Question 1

Answer: B

Answer to Question 2

Answer: A





 

Did you know?

Bacteria have been found alive in a lake buried one half mile under ice in Antarctica.

Did you know?

Limit intake of red meat and dairy products made with whole milk. Choose skim milk, low-fat or fat-free dairy products. Limit fried food. Use healthy oils when cooking.

Did you know?

The B-complex vitamins and vitamin C are not stored in the body and must be replaced each day.

Did you know?

Adults are resistant to the bacterium that causes Botulism. These bacteria thrive in honey – therefore, honey should never be given to infants since their immune systems are not yet resistant.

Did you know?

Coca-Cola originally used coca leaves and caffeine from the African kola nut. It was advertised as a therapeutic agent and "pickerupper." Eventually, its formulation was changed, and the coca leaves were removed because of the effects of regulation on cocaine-related products.

For a complete list of videos, visit our video library