Author Question: Progress payments are made to the contractor based upon: A. an estimate of the work done as ... (Read 86 times)

gbarreiro

  • Hero Member
  • *****
  • Posts: 566
Progress payments are made to the contractor based upon:
 
  A. an estimate of the work done as submitted by the resident project representative.
   B. a predetermined payment schedule based upon the progress schedule.
   C. the contractor's estimate of the work done each month.
   D. invoices submitted to the resident project representative.
   E. none of the above.

Question 2

Under the Truth in Negotiations Act how long do contracting officers have to issue a decision on a claim?
 
  What will be an ideal response?



sultana.d

  • Sr. Member
  • ****
  • Posts: 320
Answer to Question 1

A

Answer to Question 2

Under the Truth in Negotiations Act contracting officers are required to issue a decision on a claim within sixty days.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

Cutaneous mucormycosis is a rare fungal infection that has been fatal in at least 29% of cases, and in as many as 83% of cases, depending on the patient's health prior to infection. It has occurred often after natural disasters such as tornados, and early treatment is essential.

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

Parkinson's disease is both chronic and progressive. This means that it persists over a long period of time and that its symptoms grow worse over time.

Did you know?

When taking monoamine oxidase inhibitors, people should avoid a variety of foods, which include alcoholic beverages, bean curd, broad (fava) bean pods, cheese, fish, ginseng, protein extracts, meat, sauerkraut, shrimp paste, soups, and yeast.

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

For a complete list of videos, visit our video library