Progress payments are made to the contractor based upon:
 
  A. an estimate of the work done as submitted by the resident project representative.
   B. a predetermined payment schedule based upon the progress schedule.
   C. the contractor's estimate of the work done each month.
   D. invoices submitted to the resident project representative.
   E. none of the above.

Question 2

Under the Truth in Negotiations Act how long do contracting officers have to issue a decision on a claim?
 
  What will be an ideal response?



sultana.d

  • Sr. Member
  • ****
  • Posts: 320
Answer to Question 1

A

Answer to Question 2

Under the Truth in Negotiations Act contracting officers are required to issue a decision on a claim within sixty days.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The most destructive flu epidemic of all times in recorded history occurred in 1918, with approximately 20 million deaths worldwide.

Did you know?

When blood is exposed to air, it clots. Heparin allows the blood to come in direct contact with air without clotting.

Did you know?

The FDA recognizes 118 routes of administration.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

In ancient Rome, many of the richer people in the population had lead-induced gout. The reason for this is unclear. Lead poisoning has also been linked to madness.

For a complete list of videos, visit our video library