Author Question: The term fast track means __________. a. Design/ build b. Construction starts before the design ... (Read 335 times)

123654777

  • Hero Member
  • *****
  • Posts: 585
The term fast track means __________.
 
  a. Design/ build
  b. Construction starts before the design is complete
  c. Cost plus fixed fee
  d. None of the above

Question 2

In a Design/Bid/Build contractual arrangement, the architect signs a contract with the _________ .
 
  a. Owner
  b. Construction manager
  c. General contractor
  d. Subcontractor
  e. None of the above



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

nickk12214

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

B

Answer to Question 2

A




123654777

  • Member
  • Posts: 585
Reply 2 on: Jul 26, 2018
Wow, this really help


connor417

  • Member
  • Posts: 329
Reply 3 on: Yesterday
Gracias!

 

Did you know?

The ratio of hydrogen atoms to oxygen in water (H2O) is 2:1.

Did you know?

Automated pill dispensing systems have alarms to alert patients when the correct dosing time has arrived. Most systems work with many varieties of medications, so patients who are taking a variety of drugs can still be in control of their dose regimen.

Did you know?

Eating food that has been cooked with poppy seeds may cause you to fail a drug screening test, because the seeds contain enough opiate alkaloids to register as a positive.

Did you know?

Complications of influenza include: bacterial pneumonia, ear and sinus infections, dehydration, and worsening of chronic conditions such as asthma, congestive heart failure, or diabetes.

Did you know?

Although puberty usually occurs in the early teenage years, the world's youngest parents were two Chinese children who had their first baby when they were 8 and 9 years of age.

For a complete list of videos, visit our video library