The term fast track means __________.
 
  a. Design/ build
  b. Construction starts before the design is complete
  c. Cost plus fixed fee
  d. None of the above

Question 2

In a Design/Bid/Build contractual arrangement, the architect signs a contract with the _________ .
 
  a. Owner
  b. Construction manager
  c. General contractor
  d. Subcontractor
  e. None of the above



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

nickk12214

  • Sr. Member
  • ****
  • Posts: 332
Answer to Question 1

B

Answer to Question 2

A




123654777

  • Member
  • Posts: 585
Reply 2 on: Jul 26, 2018
YES! Correct, THANKS for helping me on my review


ghepp

  • Member
  • Posts: 361
Reply 3 on: Yesterday
Excellent

 

Did you know?

It is believed that the Incas used anesthesia. Evidence supports the theory that shamans chewed cocoa leaves and drilled holes into the heads of patients (letting evil spirits escape), spitting into the wounds they made. The mixture of cocaine, saliva, and resin numbed the site enough to allow hours of drilling.

Did you know?

The horizontal fraction bar was introduced by the Arabs.

Did you know?

Russia has the highest death rate from cardiovascular disease followed by the Ukraine, Romania, Hungary, and Poland.

Did you know?

The strongest synthetic topical retinoid drug available, tazarotene, is used to treat sun-damaged skin, acne, and psoriasis.

Did you know?

More than 20 million Americans cite use of marijuana within the past 30 days, according to the National Survey on Drug Use and Health (NSDUH). More than 8 million admit to using it almost every day.

For a complete list of videos, visit our video library