Author Question: Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a ... (Read 13 times)

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a project meeting in order for all personnel to have ample time to review the information.
 
  What will be an ideal response?

Question 2

How does the detail in a short interval schedule generally compare to the level of detail contained in the project schedule?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

While the suggestion may seem reasonable at first glance, one must realize that
the purpose of the short interval schedule is to serve as a planning document for the
upcoming week. If a schedule is prepared on a Monday for the following Monday,
assumptions must be made about the extent of work that will be accomplished by Friday.
Needless to say, at the level of detail that such schedules are prepared, many activities
will not be scheduled with accuracy. If many activities are improperly represented when
work begins on the following Monday, the utility or value of the short interval schedule is
drastically reduced. The schedule must be prepared after most of the work week activities
have taken place as this is the only way to assure its accuracy.

Answer to Question 2

The level of detail in a short interval schedule is considerably more involved
than that of the project schedule. For example, with a one or two year project schedule it
may be possible to tell in relative terms (approximately which week) certain tasks will be
performed. The short interval schedule, on the other hand, will specify the specific day of
the week when activities are to take place. A craft supervisor will be able to plan
activities by using a short interval schedule, but the project schedule will not contain
sufficient detail for this to occur.
Additional planning would be required for the supervisor. Of course, this is not the intent
of the project schedule. The project schedule will present information about general tasks
to be performed, but the short interval schedule will present information about the tasks
to be performed by a particular crew.





 

Did you know?

In 2012, nearly 24 milliion Americans, aged 12 and older, had abused an illicit drug, according to the National Institute on Drug Abuse (NIDA).

Did you know?

The horizontal fraction bar was introduced by the Arabs.

Did you know?

Lower drug doses for elderly patients should be used first, with titrations of the dose as tolerated to prevent unwanted drug-related pharmacodynamic effects.

Did you know?

Approximately 15–25% of recognized pregnancies end in miscarriage. However, many miscarriages often occur before a woman even knows she is pregnant.

Did you know?

For about 100 years, scientists thought that peptic ulcers were caused by stress, spicy food, and alcohol. Later, researchers added stomach acid to the list of causes and began treating ulcers with antacids. Now it is known that peptic ulcers are predominantly caused by Helicobacter pylori, a spiral-shaped bacterium that normally exist in the stomach.

For a complete list of videos, visit our video library