Author Question: Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a ... (Read 51 times)

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a project meeting in order for all personnel to have ample time to review the information.
 
  What will be an ideal response?

Question 2

How does the detail in a short interval schedule generally compare to the level of detail contained in the project schedule?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

While the suggestion may seem reasonable at first glance, one must realize that
the purpose of the short interval schedule is to serve as a planning document for the
upcoming week. If a schedule is prepared on a Monday for the following Monday,
assumptions must be made about the extent of work that will be accomplished by Friday.
Needless to say, at the level of detail that such schedules are prepared, many activities
will not be scheduled with accuracy. If many activities are improperly represented when
work begins on the following Monday, the utility or value of the short interval schedule is
drastically reduced. The schedule must be prepared after most of the work week activities
have taken place as this is the only way to assure its accuracy.

Answer to Question 2

The level of detail in a short interval schedule is considerably more involved
than that of the project schedule. For example, with a one or two year project schedule it
may be possible to tell in relative terms (approximately which week) certain tasks will be
performed. The short interval schedule, on the other hand, will specify the specific day of
the week when activities are to take place. A craft supervisor will be able to plan
activities by using a short interval schedule, but the project schedule will not contain
sufficient detail for this to occur.
Additional planning would be required for the supervisor. Of course, this is not the intent
of the project schedule. The project schedule will present information about general tasks
to be performed, but the short interval schedule will present information about the tasks
to be performed by a particular crew.





 

Did you know?

Coca-Cola originally used coca leaves and caffeine from the African kola nut. It was advertised as a therapeutic agent and "pickerupper." Eventually, its formulation was changed, and the coca leaves were removed because of the effects of regulation on cocaine-related products.

Did you know?

Drug-induced pharmacodynamic effects manifested in older adults include drug-induced renal toxicity, which can be a major factor when these adults are experiencing other kidney problems.

Did you know?

The immune system needs 9.5 hours of sleep in total darkness to recharge completely.

Did you know?

For pediatric patients, intravenous fluids are the most commonly cited products involved in medication errors that are reported to the USP.

Did you know?

An identified risk factor for osteoporosis is the intake of excessive amounts of vitamin A. Dietary intake of approximately double the recommended daily amount of vitamin A, by women, has been shown to reduce bone mineral density and increase the chances for hip fractures compared with women who consumed the recommended daily amount (or less) of vitamin A.

For a complete list of videos, visit our video library