Author Question: Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a ... (Read 22 times)

D2AR0N

  • Hero Member
  • *****
  • Posts: 561
Discuss the suggestion of preparing short interval schedules one week prior to discussing them at a project meeting in order for all personnel to have ample time to review the information.
 
  What will be an ideal response?

Question 2

How does the detail in a short interval schedule generally compare to the level of detail contained in the project schedule?
 
  What will be an ideal response?



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Jmfn03

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

While the suggestion may seem reasonable at first glance, one must realize that
the purpose of the short interval schedule is to serve as a planning document for the
upcoming week. If a schedule is prepared on a Monday for the following Monday,
assumptions must be made about the extent of work that will be accomplished by Friday.
Needless to say, at the level of detail that such schedules are prepared, many activities
will not be scheduled with accuracy. If many activities are improperly represented when
work begins on the following Monday, the utility or value of the short interval schedule is
drastically reduced. The schedule must be prepared after most of the work week activities
have taken place as this is the only way to assure its accuracy.

Answer to Question 2

The level of detail in a short interval schedule is considerably more involved
than that of the project schedule. For example, with a one or two year project schedule it
may be possible to tell in relative terms (approximately which week) certain tasks will be
performed. The short interval schedule, on the other hand, will specify the specific day of
the week when activities are to take place. A craft supervisor will be able to plan
activities by using a short interval schedule, but the project schedule will not contain
sufficient detail for this to occur.
Additional planning would be required for the supervisor. Of course, this is not the intent
of the project schedule. The project schedule will present information about general tasks
to be performed, but the short interval schedule will present information about the tasks
to be performed by a particular crew.





 

Did you know?

Adolescents often feel clumsy during puberty because during this time of development, their hands and feet grow faster than their arms and legs do. The body is therefore out of proportion. One out of five adolescents actually experiences growing pains during this period.

Did you know?

Side effects from substance abuse include nausea, dehydration, reduced productivitiy, and dependence. Though these effects usually worsen over time, the constant need for the substance often overcomes rational thinking.

Did you know?

The first oncogene was discovered in 1970 and was termed SRC (pronounced "SARK").

Did you know?

It is widely believed that giving a daily oral dose of aspirin to heart attack patients improves their chances of survival because the aspirin blocks the formation of new blood clots.

Did you know?

Hyperthyroidism leads to an increased rate of metabolism and affects about 1% of women but only 0.1% of men. For most people, this increased metabolic rate causes the thyroid gland to become enlarged (known as a goiter).

For a complete list of videos, visit our video library