Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.


To help get organized, Grace prepares a bar graph that visually shows when her tasks are supposed to be done and compares that with the actual progress on each. Now she can easily assess which projects are ahead of, behind, or on schedule. Grace has used which scheduling technique?
◦ Gantt chart
◦ PERT network analysis
◦ load chart
◦ time series analysis
◦ linear programming


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by abarnes on Oct 25, 2019

bfulkerson77

  • Sr. Member
  • ****
  • Posts: 331
Lorsum iprem. Lorsus sur ipci. Lorsem sur iprem. Lorsum sur ipdi, lorsem sur ipci. Lorsum sur iprium, valum sur ipci et, vala sur ipci. Lorsem sur ipci, lorsa sur iprem. Valus sur ipdi. Lorsus sur iprium nunc, valem sur iprium. Valem sur ipdi. Lorsa sur iprium. Lorsum sur iprium. Valem sur ipdi. Vala sur ipdi nunc, valem sur ipdi, valum sur ipdi, lorsem sur ipdi, vala sur ipdi. Valem sur iprem nunc, lorsa sur iprium. Valum sur ipdi et, lorsus sur ipci. Valem sur iprem. Valem sur ipci. Lorsa sur iprium. Lorsem sur ipci, valus sur iprem. Lorsem sur iprem nunc, valus sur iprium.
Answer Preview
Only 50% of students answer this correctly



dakota nelson

  • Hero Member
  • *****
  • Posts: 604
Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.


The flow chart that Linda is using depicts the sequence of activities necessary to construct the office building and the time and costs associated with each activity. Linda is using ________.
◦ breakeven analysis
◦ PERT network analysis
◦ linear programming
◦ a Gantt chart
◦ time series analysis




nmorano1

  • Hero Member
  • *****
  • Posts: 598
Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.


The time or resources that are required to progress from one event to another in Linda's flow chart are called ________.
◦ load factors
◦ events
◦ slack time
◦ milestones
◦ activities




bcretired

  • Hero Member
  • *****
  • Posts: 525
Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.


The longest or most time-consuming sequence of events or activities time in Linda's flow chart is called ________.
◦ a scheduling bottleneck
◦ the time series progression
◦ the critical path
◦ crunch time
◦ slack time




jjjetplane

  • Hero Member
  • *****
  • Posts: 556
Scheduling Tools (Scenario)
Grace has just graduated from university and is totally overwhelmed by her first management job. When she was in school, she could work on projects one at a time; but now she must juggle several projects, each of which has multiple activities. Grace is amazed to find that her supervisor, Linda, has everything planned in a flow chart diagram. Linda's current project is to oversee the construction of an office building, and Grace is determined to understand all of the major activities and potential problems so that she can be more proactive.


In Linda's flow chart, the amount of time that an individual activity can be delayed without delaying the whole project is called ________.
◦ the critical path
◦ slack time
◦ crash time
◦ delay time
◦ down time




 

Did you know?

In 2006, a generic antinausea drug named ondansetron was approved. It is used to stop nausea and vomiting associated with surgery, chemotherapy, and radiation therapy.

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

Did you know?

Although the Roman numeral for the number 4 has always been taught to have been "IV," according to historians, the ancient Romans probably used "IIII" most of the time. This is partially backed up by the fact that early grandfather clocks displayed IIII for the number 4 instead of IV. Early clockmakers apparently thought that the IIII balanced out the VIII (used for the number 8) on the clock face and that it just looked better.

Did you know?

Fungal nail infections account for up to 30% of all skin infections. They affect 5% of the general population—mostly people over the age of 70.

Did you know?

Essential fatty acids have been shown to be effective against ulcers, asthma, dental cavities, and skin disorders such as acne.

For a complete list of videos, visit our video library