Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the project finishing time is
◦ 20 hours.
◦ 18 hours.
◦ 17 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 5 hours.
◦ 3 hours.
◦ 7 hours.
◦ 1 hour.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

samiel-sayed

  • Sr. Member
  • ****
  • Posts: 337

itsmyluck

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors, the project finishing time is
◦ 12 hours.
◦ 13 hours.
◦ 11 hours.
◦ 14 hours.
◦ none of these

Question 2

A project consists of five tasks. The lengths of the tasks (in hours) are 5, 4, 4, 3, and 3. The tasks are all independent (i.e., there are no precedence relations).

Using the critical-path algorithm to schedule the project with two processors, the finishing time is
◦ 12 hours.
◦ 9 hours.
◦ 10 hours.
◦ 11 hours.
◦ none of these



olderstudent

  • Sr. Member
  • ****
  • Posts: 339

 

Did you know?

Although the Roman numeral for the number 4 has always been taught to have been "IV," according to historians, the ancient Romans probably used "IIII" most of the time. This is partially backed up by the fact that early grandfather clocks displayed IIII for the number 4 instead of IV. Early clockmakers apparently thought that the IIII balanced out the VIII (used for the number 8) on the clock face and that it just looked better.

Did you know?

A cataract is a clouding of the eyes' natural lens. As we age, some clouding of the lens may occur. The first sign of a cataract is usually blurry vision. Although glasses and other visual aids may at first help a person with cataracts, surgery may become inevitable. Cataract surgery is very successful in restoring vision, and it is the most frequently performed surgery in the United States.

Did you know?

Patients who have been on total parenteral nutrition for more than a few days may need to have foods gradually reintroduced to give the digestive tract time to start working again.

Did you know?

It is important to read food labels and choose foods with low cholesterol and saturated trans fat. You should limit saturated fat to no higher than 6% of daily calories.

Did you know?

Though methadone is often used to treat dependency on other opioids, the drug itself can be abused. Crushing or snorting methadone can achieve the opiate "rush" desired by addicts. Improper use such as these can lead to a dangerous dependency on methadone. This drug now accounts for nearly one-third of opioid-related deaths.

For a complete list of videos, visit our video library