Author Question: Suppose you have the following project digraph. (The numbers in parentheses represent hours.)The ... (Read 1170 times)

mmm

  • Hero Member
  • *****
  • Posts: 558

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the project finishing time is
◦ 20 hours.
◦ 18 hours.
◦ 17 hours.
◦ 19 hours.
◦ none of these

Question 2

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 5 hours.
◦ 3 hours.
◦ 7 hours.
◦ 1 hour.
◦ none of these


Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question

samiel-sayed

  • Sr. Member
  • ****
  • Posts: 337

itsmyluck

  • Hero Member
  • *****
  • Posts: 546

Question 1

Suppose you have the following project digraph. (The numbers in parentheses represent hours.)




Using the critical-path algorithm to schedule this project with three processors, the project finishing time is
◦ 12 hours.
◦ 13 hours.
◦ 11 hours.
◦ 14 hours.
◦ none of these

Question 2

A project consists of five tasks. The lengths of the tasks (in hours) are 5, 4, 4, 3, and 3. The tasks are all independent (i.e., there are no precedence relations).

Using the critical-path algorithm to schedule the project with two processors, the finishing time is
◦ 12 hours.
◦ 9 hours.
◦ 10 hours.
◦ 11 hours.
◦ none of these



olderstudent

  • Sr. Member
  • ****
  • Posts: 339

 

Did you know?

Asthma occurs in one in 11 children and in one in 12 adults. African Americans and Latinos have a higher risk for developing asthma than other groups.

Did you know?

No drugs are available to relieve parathyroid disease. Parathyroid disease is caused by a parathyroid tumor, and it needs to be removed by surgery.

Did you know?

Everyone has one nostril that is larger than the other.

Did you know?

A headache when you wake up in the morning is indicative of sinusitis. Other symptoms of sinusitis can include fever, weakness, tiredness, a cough that may be more severe at night, and a runny nose or nasal congestion.

Did you know?

Chronic necrotizing aspergillosis has a slowly progressive process that, unlike invasive aspergillosis, does not spread to other organ systems or the blood vessels. It most often affects middle-aged and elderly individuals, spreading to surrounding tissue in the lungs. The disease often does not respond to conventionally successful treatments, and requires individualized therapies in order to keep it from becoming life-threatening.

For a complete list of videos, visit our video library