Question 1
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with two processors, the project finishing time is
◦ 20 hours.
◦ 18 hours.
◦ 17 hours.
◦ 19 hours.
◦ none of these
Question 2
Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Using the critical-path algorithm to schedule this project with two processors, the total combined idle time of the two processors is
◦ 5 hours.
◦ 3 hours.
◦ 7 hours.
◦ 1 hour.
◦ none of these