Author Question: When activity times are uncertain, an activity's most likely time is the same as its expected time. ... (Read 109 times)

newyorker26

  • Hero Member
  • *****
  • Posts: 536
When activity times are uncertain, an activity's most likely time is the same as its expected time.
  Indicate whether the statement is true or false

Question 2

In regression analysis, if the dependent variable is measured in dollars, the independent variable _____.
 a. must also be in dollars
  b. must be in some unit of currency
  c. can be any units
  d. cannot be in dollars



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

ghepp

  • Sr. Member
  • ****
  • Posts: 361
Answer to Question 1

F

Answer to Question 2

c





 

Did you know?

The highest suicide rate in the United States is among people ages 65 years and older. Almost 15% of people in this age group commit suicide every year.

Did you know?

Every 10 seconds, a person in the United States goes to the emergency room complaining of head pain. About 1.2 million visits are for acute migraine attacks.

Did you know?

More than one-third of adult Americans are obese. Diseases that kill the largest number of people annually, such as heart disease, cancer, diabetes, stroke, and hypertension, can be attributed to diet.

Did you know?

In inpatient settings, adverse drug events account for an estimated one in three of all hospital adverse events. They affect approximately 2 million hospital stays every year, and prolong hospital stays by between one and five days.

Did you know?

By definition, when a medication is administered intravenously, its bioavailability is 100%.

For a complete list of videos, visit our video library