Author Question: The latest finish time for an activity is the largest of the latest start times for all activities ... (Read 251 times)

nenivikky

  • Hero Member
  • *****
  • Posts: 516
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
  Indicate whether the statement is true or false

Question 2

A descriptive measure that is computed from a sample is called a statistic.
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

shayla

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

F

Answer to Question 2

T




nenivikky

  • Member
  • Posts: 516
Reply 2 on: Jun 24, 2018
Excellent


bdobbins

  • Member
  • Posts: 326
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

More than nineteen million Americans carry the factor V gene that causes blood clots, pulmonary embolism, and heart disease.

Did you know?

Complications of influenza include: bacterial pneumonia, ear and sinus infections, dehydration, and worsening of chronic conditions such as asthma, congestive heart failure, or diabetes.

Did you know?

There are more bacteria in your mouth than there are people in the world.

Did you know?

The most common childhood diseases include croup, chickenpox, ear infections, flu, pneumonia, ringworm, respiratory syncytial virus, scabies, head lice, and asthma.

Did you know?

A strange skin disease referred to as Morgellons has occurred in the southern United States and in California. Symptoms include slowly healing sores, joint pain, persistent fatigue, and a sensation of things crawling through the skin. Another symptom is strange-looking, threadlike extrusions coming out of the skin.

For a complete list of videos, visit our video library