Author Question: To calculate an activity's latest finish time, you should consider its a. predecessors' latest ... (Read 210 times)

pane00

  • Hero Member
  • *****
  • Posts: 579
To calculate an activity's latest finish time, you should consider its
 a. predecessors' latest finish times c. successors' earliest start times
  b. predecessors' latest start times d. successors' latest start times

Question 2

The equation that describes how the dependent variable (y) is related to the independent variable (x) is called _____.
 a. the correlation model
  b. the regression model
  c. correlation analysis
  d. None of the answers is correct.



matt95

  • Sr. Member
  • ****
  • Posts: 317
Answer to Question 1

D

Answer to Question 2

b



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

There are more nerve cells in one human brain than there are stars in the Milky Way.

Did you know?

Atropine, along with scopolamine and hyoscyamine, is found in the Datura stramonium plant, which gives hallucinogenic effects and is also known as locoweed.

Did you know?

All adults should have their cholesterol levels checked once every 5 years. During 2009–2010, 69.4% of Americans age 20 and older reported having their cholesterol checked within the last five years.

Did you know?

The Centers for Disease Control and Prevention (CDC) was originally known as the Communicable Disease Center, which was formed to fight malaria. It was originally headquartered in Atlanta, Georgia, since the Southern states faced the worst threat from malaria.

Did you know?

Your heart beats over 36 million times a year.

For a complete list of videos, visit our video library