Author Question: To calculate an activity's latest finish time, you should consider its a. predecessors' latest ... (Read 252 times)

pane00

  • Hero Member
  • *****
  • Posts: 579
To calculate an activity's latest finish time, you should consider its
 a. predecessors' latest finish times c. successors' earliest start times
  b. predecessors' latest start times d. successors' latest start times

Question 2

The equation that describes how the dependent variable (y) is related to the independent variable (x) is called _____.
 a. the correlation model
  b. the regression model
  c. correlation analysis
  d. None of the answers is correct.



matt95

  • Sr. Member
  • ****
  • Posts: 317
Answer to Question 1

D

Answer to Question 2

b



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

More than 2,500 barbiturates have been synthesized. At the height of their popularity, about 50 were marketed for human use.

Did you know?

Human neurons are so small that they require a microscope in order to be seen. However, some neurons can be up to 3 feet long, such as those that extend from the spinal cord to the toes.

Did you know?

Asthma cases in Americans are about 75% higher today than they were in 1980.

Did you know?

There are more sensory neurons in the tongue than in any other part of the body.

Did you know?

Asthma is the most common chronic childhood disease in the world. Most children who develop asthma have symptoms before they are 5 years old.

For a complete list of videos, visit our video library