Author Question: To calculate an activity's latest finish time, you should consider its a. predecessors' latest ... (Read 217 times)

pane00

  • Hero Member
  • *****
  • Posts: 579
To calculate an activity's latest finish time, you should consider its
 a. predecessors' latest finish times c. successors' earliest start times
  b. predecessors' latest start times d. successors' latest start times

Question 2

The equation that describes how the dependent variable (y) is related to the independent variable (x) is called _____.
 a. the correlation model
  b. the regression model
  c. correlation analysis
  d. None of the answers is correct.



matt95

  • Sr. Member
  • ****
  • Posts: 317
Answer to Question 1

D

Answer to Question 2

b



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The modern decimal position system was the invention of the Hindus (around 800 AD), involving the placing of numerals to indicate their value (units, tens, hundreds, and so on).

Did you know?

Anti-aging claims should not ever be believed. There is no supplement, medication, or any other substance that has been proven to slow or stop the aging process.

Did you know?

The first oncogene was discovered in 1970 and was termed SRC (pronounced "SARK").

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

Your heart beats over 36 million times a year.

For a complete list of videos, visit our video library