Author Question: The latest finish time for an activity is the largest of the latest start times for all activities ... (Read 634 times)

nenivikky

  • Hero Member
  • *****
  • Posts: 516
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
  Indicate whether the statement is true or false

Question 2

A descriptive measure that is computed from a sample is called a statistic.
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

shayla

  • Sr. Member
  • ****
  • Posts: 323
Answer to Question 1

F

Answer to Question 2

T




nenivikky

  • Member
  • Posts: 516
Reply 2 on: Jun 24, 2018
Thanks for the timely response, appreciate it


alvinum

  • Member
  • Posts: 317
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

The U.S. Preventive Services Task Force recommends that all women age 65 years of age or older should be screened with bone densitometry.

Did you know?

Parkinson's disease is both chronic and progressive. This means that it persists over a long period of time and that its symptoms grow worse over time.

Did you know?

Individuals are never “cured” of addictions. Instead, they learn how to manage their disease to lead healthy, balanced lives.

Did you know?

About 3% of all pregnant women will give birth to twins, which is an increase in rate of nearly 60% since the early 1980s.

Did you know?

The heart is located in the center of the chest, with part of it tipped slightly so that it taps against the left side of the chest.

For a complete list of videos, visit our video library