Author Question: In Naples v. Keystone Building and Development Corp in which the Naples sued Keystone for the cost ... (Read 83 times)

jhjkgdfhk

  • Hero Member
  • *****
  • Posts: 569
In Naples v. Keystone Building and Development Corp in which the Naples sued Keystone for the cost of repairing major problems in the house Keystone built for the Naples, the state supreme court held that:
 a. since there was no contradiction of the expert witness's testimony regarding the cost of repairs, the Naples should be compensated adequately for the damages caused by the defendants' breach of contract
  b. since there was no contradiction of the expert witness's testimony regarding the cost of repairs, the Naples should not be compensated adequately for the damages caused by the defendants' breach of contract
  c. since there was a contradiction of the expert witness's testimony regarding the cost of repairs, the Naples should not be compensated adequately for the damages caused by the defendants' breach of contract
  d. since the defendant did not produce an expert witness, the Naples should be compensated adequately for the damages caused by the defendants' breach of contract
  e. none of the other choices are correct

Question 2

In Naples v. Keystone Building and Development Corp in which the Naples sued Keystone for the cost of repairing major problems in the house Keystone built for the Naples, the state supreme court held that:
 a. the Naples should be awarded the full amount necessary to restore them to the position they would have been in had the contract been properly performed
  b. the Naples need not be awarded the full amount necessary to restore them to the position they would have been in had the contract been properly performed
  c. the Naples should be awarded the half the amount necessary to restore them to the position they would have been in had the contract been properly performed
  d. the Naples should be awarded 20 of the full amount necessary to restore them to the position they would have been in had the contract been properly performed
  e. none of the other choices are correct



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

mcni194

  • Sr. Member
  • ****
  • Posts: 311
Answer to Question 1

a

Answer to Question 2

a




jhjkgdfhk

  • Member
  • Posts: 569
Reply 2 on: Jun 24, 2018
Gracias!


samiel-sayed

  • Member
  • Posts: 337
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

There can actually be a 25-hour time difference between certain locations in the world. The International Date Line passes between the islands of Samoa and American Samoa. It is not a straight line, but "zig-zags" around various island chains. Therefore, Samoa and nearby islands have one date, while American Samoa and nearby islands are one day behind. Daylight saving time is used in some islands, but not in others—further shifting the hours out of sync with natural time.

Did you know?

Cancer has been around as long as humankind, but only in the second half of the twentieth century did the number of cancer cases explode.

Did you know?

Bacteria have been found alive in a lake buried one half mile under ice in Antarctica.

Did you know?

Russia has the highest death rate from cardiovascular disease followed by the Ukraine, Romania, Hungary, and Poland.

Did you know?

Parkinson's disease is both chronic and progressive. This means that it persists over a long period of time and that its symptoms grow worse over time.

For a complete list of videos, visit our video library