Activities without any slack in a PERT network are by definition on the critical path.
 a. True
  b. False
 Indicate whether the statement is true or false

Question 2

The allocation of distribution tasks should include consideration of all of the following except:
 a. Number of levels in the channel.
  b. The saturation at the various levels.
  c. The number of channel managers at each level.
  d. Types of intermediaries at each level.
  e. The selective number of intermediaries at various levels.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Leostella20

  • Sr. Member
  • ****
  • Posts: 337
Answer to Question 1

True

Answer to Question 2

C





 

Did you know?

The shortest mature adult human of whom there is independent evidence was Gul Mohammed in India. In 1990, he was measured in New Delhi and stood 22.5 inches tall.

Did you know?

A recent study has found that following a diet rich in berries may slow down the aging process of the brain. This diet apparently helps to keep dopamine levels much higher than are seen in normal individuals who do not eat berries as a regular part of their diet as they enter their later years.

Did you know?

It is important to read food labels and choose foods with low cholesterol and saturated trans fat. You should limit saturated fat to no higher than 6% of daily calories.

Did you know?

Excessive alcohol use costs the country approximately $235 billion every year.

Did you know?

Medication errors are more common among seriously ill patients than with those with minor conditions.

For a complete list of videos, visit our video library