Activities without any slack in a PERT network are by definition on the critical path.
 a. True
  b. False
 Indicate whether the statement is true or false

Question 2

The allocation of distribution tasks should include consideration of all of the following except:
 a. Number of levels in the channel.
  b. The saturation at the various levels.
  c. The number of channel managers at each level.
  d. Types of intermediaries at each level.
  e. The selective number of intermediaries at various levels.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Leostella20

  • Sr. Member
  • ****
  • Posts: 337
Answer to Question 1

True

Answer to Question 2

C





 

Did you know?

The most dangerous mercury compound, dimethyl mercury, is so toxic that even a few microliters spilled on the skin can cause death. Mercury has been shown to accumulate in higher amounts in the following types of fish than other types: swordfish, shark, mackerel, tilefish, crab, and tuna.

Did you know?

Earwax has antimicrobial properties that reduce the viability of bacteria and fungus in the human ear.

Did you know?

The Romans did not use numerals to indicate fractions but instead used words to indicate parts of a whole.

Did you know?

The strongest synthetic topical retinoid drug available, tazarotene, is used to treat sun-damaged skin, acne, and psoriasis.

Did you know?

More than 30% of American adults, and about 12% of children utilize health care approaches that were developed outside of conventional medicine.

For a complete list of videos, visit our video library