Author Question: The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and ... (Read 105 times)

brutforce

  • Hero Member
  • *****
  • Posts: 540
The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and resource assignments. It is denoted as ________ WBS.
 
  A) test
  B) baseline
  C) standard
  D) benchmark

Question 2

There are four entities that should be modeled in the ER diagram.
 
  Indicate whether the statement is true or false


fatboyy09

  • Sr. Member
  • ****
  • Posts: 358
Answer to Question 1

B

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

To combat osteoporosis, changes in lifestyle and diet are recommended. At-risk patients should include 1,200 to 1,500 mg of calcium daily either via dietary means or with supplements.

Did you know?

To prove that stomach ulcers were caused by bacteria and not by stress, a researcher consumed an entire laboratory beaker full of bacterial culture. After this, he did indeed develop stomach ulcers, and won the Nobel Prize for his discovery.

Did you know?

A headache when you wake up in the morning is indicative of sinusitis. Other symptoms of sinusitis can include fever, weakness, tiredness, a cough that may be more severe at night, and a runny nose or nasal congestion.

Did you know?

The Babylonians wrote numbers in a system that used 60 as the base value rather than the number 10. They did not have a symbol for "zero."

Did you know?

Hyperthyroidism leads to an increased rate of metabolism and affects about 1% of women but only 0.1% of men. For most people, this increased metabolic rate causes the thyroid gland to become enlarged (known as a goiter).

For a complete list of videos, visit our video library