Author Question: The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and ... (Read 110 times)

brutforce

  • Hero Member
  • *****
  • Posts: 540
The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and resource assignments. It is denoted as ________ WBS.
 
  A) test
  B) baseline
  C) standard
  D) benchmark

Question 2

There are four entities that should be modeled in the ER diagram.
 
  Indicate whether the statement is true or false


fatboyy09

  • Sr. Member
  • ****
  • Posts: 358
Answer to Question 1

B

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

Aspirin may benefit 11 different cancers, including those of the colon, pancreas, lungs, prostate, breasts, and leukemia.

Did you know?

Computer programs are available that crosscheck a new drug's possible trade name with all other trade names currently available. These programs detect dangerous similarities between names and alert the manufacturer of the drug.

Did you know?

The types of cancer that alpha interferons are used to treat include hairy cell leukemia, melanoma, follicular non-Hodgkin's lymphoma, and AIDS-related Kaposi's sarcoma.

Did you know?

About 80% of major fungal systemic infections are due to Candida albicans. Another form, Candida peritonitis, occurs most often in postoperative patients. A rare disease, Candida meningitis, may follow leukemia, kidney transplant, other immunosuppressed factors, or when suffering from Candida septicemia.

Did you know?

More than 20 million Americans cite use of marijuana within the past 30 days, according to the National Survey on Drug Use and Health (NSDUH). More than 8 million admit to using it almost every day.

For a complete list of videos, visit our video library