Author Question: The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and ... (Read 126 times)

brutforce

  • Hero Member
  • *****
  • Posts: 540
The final work breakdown structure (WBS) plan shows planned tasks, dependencies, durations, and resource assignments. It is denoted as ________ WBS.
 
  A) test
  B) baseline
  C) standard
  D) benchmark

Question 2

There are four entities that should be modeled in the ER diagram.
 
  Indicate whether the statement is true or false


fatboyy09

  • Sr. Member
  • ****
  • Posts: 358
Answer to Question 1

B

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question


 

Did you know?

All adults should have their cholesterol levels checked once every 5 years. During 2009–2010, 69.4% of Americans age 20 and older reported having their cholesterol checked within the last five years.

Did you know?

Asthma cases in Americans are about 75% higher today than they were in 1980.

Did you know?

Although puberty usually occurs in the early teenage years, the world's youngest parents were two Chinese children who had their first baby when they were 8 and 9 years of age.

Did you know?

More than 34,000 trademarked medication names and more than 10,000 generic medication names are in use in the United States.

Did you know?

Oliver Wendell Holmes is credited with introducing the words "anesthesia" and "anesthetic" into the English language in 1846.

For a complete list of videos, visit our video library