Author Question: If a defined project is determined to be feasible in the systems development life cycle (SDLC), the ... (Read 85 times)

Collmarie

  • Hero Member
  • *****
  • Posts: 569
If a defined project is determined to be feasible in the systems development life cycle (SDLC), the next step is to ________.
 
  A) create and test components
  B) form the project team
  C) maintain the system
  D) assess process results

Question 2

Entities are like __________; they are persons, places, or things.
 
  Fill in the blanks with correct word



vickyvicksss

  • Sr. Member
  • ****
  • Posts: 351
Answer to Question 1

B

Answer to Question 2

nouns



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

There are more sensory neurons in the tongue than in any other part of the body.

Did you know?

No drugs are available to relieve parathyroid disease. Parathyroid disease is caused by a parathyroid tumor, and it needs to be removed by surgery.

Did you know?

All adverse reactions are commonly charted in red ink in the patient's record and usually are noted on the front of the chart. Failure to follow correct documentation procedures may result in malpractice lawsuits.

Did you know?

The first war in which wide-scale use of anesthetics occurred was the Civil War, and 80% of all wounds were in the extremities.

Did you know?

Although the Roman numeral for the number 4 has always been taught to have been "IV," according to historians, the ancient Romans probably used "IIII" most of the time. This is partially backed up by the fact that early grandfather clocks displayed IIII for the number 4 instead of IV. Early clockmakers apparently thought that the IIII balanced out the VIII (used for the number 8) on the clock face and that it just looked better.

For a complete list of videos, visit our video library