Author Question: In case of task dependencies in a project, all tasks must begin and end at the same time. ... (Read 76 times)

Jipu 123

  • Hero Member
  • *****
  • Posts: 569
In case of task dependencies in a project, all tasks must begin and end at the same time.
 
  Indicate whether the statement is true or false

Question 2

The critical path determines the earliest date by considering the shortest path through the network of activities.
 
  Indicate whether the statement is true or false



zoeyesther

  • Sr. Member
  • ****
  • Posts: 315
Answer to Question 1

FALSE

Answer to Question 2

FALSE



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

People who have myopia, or nearsightedness, are not able to see objects at a distance but only up close. It occurs when the cornea is either curved too steeply, the eye is too long, or both. This condition is progressive and worsens with time. More than 100 million people in the United States are nearsighted, but only 20% of those are born with the condition. Diet, eye exercise, drug therapy, and corrective lenses can all help manage nearsightedness.

Did you know?

The first documented use of surgical anesthesia in the United States was in Connecticut in 1844.

Did you know?

Thyroid conditions cause a higher risk of fibromyalgia and chronic fatigue syndrome.

Did you know?

In ancient Rome, many of the richer people in the population had lead-induced gout. The reason for this is unclear. Lead poisoning has also been linked to madness.

Did you know?

A seasonal flu vaccine is the best way to reduce the chances you will get seasonal influenza and spread it to others.

For a complete list of videos, visit our video library