Author Question: Work Breakdown Structure (WBS) decomposes the project into ________ with different levels for ... (Read 98 times)

Jkov05

  • Hero Member
  • *****
  • Posts: 556
Work Breakdown Structure (WBS) decomposes the project into ________ with different levels for activities.
 
  A) segments
  B) steps
  C) a hierarchy
  D) parts

Question 2

Design discovers from the inside but refines from the outside.
 
  Indicate whether the statement is true or false



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

pami445

  • Sr. Member
  • ****
  • Posts: 303
Answer to Question 1

C

Answer to Question 2

FALSE




Jkov05

  • Member
  • Posts: 556
Reply 2 on: Jul 7, 2018
Thanks for the timely response, appreciate it


daiying98

  • Member
  • Posts: 354
Reply 3 on: Yesterday
YES! Correct, THANKS for helping me on my review

 

Did you know?

There are 20 feet of blood vessels in each square inch of human skin.

Did you know?

There used to be a metric calendar, as well as metric clocks. The metric calendar, or "French Republican Calendar" divided the year into 12 months, but each month was divided into three 10-day weeks. Each day had 10 decimal hours. Each hour had 100 decimal minutes. Due to lack of popularity, the metric clocks and calendars were ended in 1795, three years after they had been first marketed.

Did you know?

Asthma occurs in one in 11 children and in one in 12 adults. African Americans and Latinos have a higher risk for developing asthma than other groups.

Did you know?

Bacteria have been found alive in a lake buried one half mile under ice in Antarctica.

Did you know?

Multiple experimental evidences have confirmed that at the molecular level, cancer is caused by lesions in cellular DNA.

For a complete list of videos, visit our video library