Author Question: The major steps in the process of justifying large-scale EC and IT projects include each of the ... (Read 218 times)

tfester

  • Hero Member
  • *****
  • Posts: 534
The major steps in the process of justifying large-scale EC and IT projects include each of the following except
 
  A) lay an appropriate foundation for analysis with your vendor, and then conduct your ROI.
  B) document and verify all figures used in the calculation. Clarify all assumptions.
  C) do not leave out strategic benefits, including long-term ones.
  D) be careful not to overestimate cost and underestimate benefits (a tendency of many managers).

Question 2

The online delivery of information for purposes of education, training, or knowledge management best describes
 
  A) edutainment.
  B) e-learning.
  C) mobile learning.
  D) location-based learning.



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

kmb352

  • Sr. Member
  • ****
  • Posts: 319
Answer to Question 1

D

Answer to Question 2

B




tfester

  • Member
  • Posts: 534
Reply 2 on: Jul 7, 2018
YES! Correct, THANKS for helping me on my review


Bigfoot1984

  • Member
  • Posts: 321
Reply 3 on: Yesterday
:D TYSM

 

Did you know?

The modern decimal position system was the invention of the Hindus (around 800 AD), involving the placing of numerals to indicate their value (units, tens, hundreds, and so on).

Did you know?

Adult head lice are gray, about ? inch long, and often have a tiny dot on their backs. A female can lay between 50 and 150 eggs within the several weeks that she is alive. They feed on human blood.

Did you know?

Most women experience menopause in their 50s. However, in 1994, an Italian woman gave birth to a baby boy when she was 61 years old.

Did you know?

Your chance of developing a kidney stone is 1 in 10. In recent years, approximately 3.7 million people in the United States were diagnosed with a kidney disease.

Did you know?

The immune system needs 9.5 hours of sleep in total darkness to recharge completely.

For a complete list of videos, visit our video library