Author Question: The S-curve in the figure above is based on _____. a. schedule data during month one b. ... (Read 70 times)

javeds

  • Hero Member
  • *****
  • Posts: 570
/
  The S-curve in the figure above is based on _____.
 
  a. schedule data during month one
  b. project schedule and actual costs during construction
  c. project schedule and estimate before construction begins
  d. tracking the project at an average pace

Question 2

Two important purposes of cost control are _____.
 
  a. staying within budget and producing historical data
  b. pricing and estimating
  c. project initiation and controlling scope of work
  d. developing preliminary reports and field estimates



snackralk

  • Sr. Member
  • ****
  • Posts: 363
Answer to Question 1

c

Answer to Question 2

a



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
 

Did you know?

The average adult has about 21 square feet of skin.

Did you know?

Allergies play a major part in the health of children. The most prevalent childhood allergies are milk, egg, soy, wheat, peanuts, tree nuts, and seafood.

Did you know?

Each year in the United States, there are approximately six million pregnancies. This means that at any one time, about 4% of women in the United States are pregnant.

Did you know?

The first monoclonal antibodies were made exclusively from mouse cells. Some are now fully human, which means they are likely to be safer and may be more effective than older monoclonal antibodies.

Did you know?

A headache when you wake up in the morning is indicative of sinusitis. Other symptoms of sinusitis can include fever, weakness, tiredness, a cough that may be more severe at night, and a runny nose or nasal congestion.

For a complete list of videos, visit our video library