Author Question: When work is completed under the original estimate, the major problem is _____. a. material costs ... (Read 48 times)

maychende

  • Hero Member
  • *****
  • Posts: 556
When work is completed under the original estimate, the major problem is _____.
 
  a. material costs are not accurate
  b. poor historical data
  c. bids are not competitive
  d. profits are limited

Question 2

Determining probable construction costs are _____ estimates.
 
  a. pre-construction
  b. preliminary
  c. detailed
  d. resource



Related Topics

Need homework help now?

Ask unlimited questions for free

Ask a Question
Marked as best answer by a Subject Expert

Gabe

  • Sr. Member
  • ****
  • Posts: 321
Answer to Question 1

c

Answer to Question 2

a




maychende

  • Member
  • Posts: 556
Reply 2 on: Jul 24, 2018
Thanks for the timely response, appreciate it


Jossy

  • Member
  • Posts: 336
Reply 3 on: Yesterday
Wow, this really help

 

Did you know?

The eye muscles are the most active muscles in the whole body. The external muscles that move the eyes are the strongest muscles in the human body for the job they have to do. They are 100 times more powerful than they need to be.

Did you know?

In inpatient settings, adverse drug events account for an estimated one in three of all hospital adverse events. They affect approximately 2 million hospital stays every year, and prolong hospital stays by between one and five days.

Did you know?

The U.S. Preventive Services Task Force recommends that all women age 65 years of age or older should be screened with bone densitometry.

Did you know?

The newest statin drug, rosuvastatin, has been called a superstatin because it appears to reduce LDL cholesterol to a greater degree than the other approved statin drugs.

Did you know?

People about to have surgery must tell their health care providers about all supplements they take.

For a complete list of videos, visit our video library